Still to come: ductwork connections, thermostat replacements, connecting the well plumbing, finalizing the wiring and covering the pipes on the front of the house, removal of the second HVAC system that is still keeping the bedroom cool, and connecting the two separate systems together with ducts and motorized dampers. Should be done this week!
Before the changes. Old gas water heater on the left, water softener and furnace unit.

Disassembling the furnace.

Furnace removed, platform below going soon.

Here's what was under the platform...more old rat nests and the air return from the house.

End of day, platform gone, new electric water heater installed, geo main unit and the softener.